Press release -
Passengers thanked as Stourbridge to Birmingham line reopens
Upgrades to improve journeys for passengers between Stourbridge and Birmingham Snow Hill are now complete.
The stretch of railway reopened today (Friday 1 November) after Network Rail worked round-the-clock over the last five days to replace track and improve drainage, work which will help keep the railway and journeys through the area safe and reliable.
During the closure, Network Rail engineers replaced 64 sleepers, improved track drainage and upgraded level crossing equipment, including barriers, lighting and cables at Cradley Heath.
More than 250 tonnes of ballast (the stones in between the track and sleepers) were also used across a two-mile section of track. Special trains called ‘tamping machines’ then passed over the track to vibrate the stones to pack them tightly together. This provides a firm foundation for the railway track and sleepers to sit on.
Adam Checkley, infrastructure director for Network Rail, said: “I’d like to thank passengers for their patience while we completed essential maintenance work to the section of track between Langley Green and Stourbridge.
“This was essential work, carefully planned to cause the least disruption, which will help make journeys smoother and more reliable for years to come.”
Jonny Wiseman, customer experience director for West Midlands Railway, said: “We are grateful for our passengers’ patience while Network Rail completed these essential engineering works over the past week. We’re pleased the line has now reopened as planned and our normal timetable is now back in operation.”
Michael Stewart, commercial & customer strategy director at Chiltern Railways, said: “The engineering works by Network Rail will help keep the railway safe and ensure journeys are more reliable in the future.
“I’d like to thank customers for their understanding as the upgrades are now complete and the line has been reopened.”
Passengers can plan their journeys and check for the latest travel information at www.nationalrail.co.uk.
Topics
Categories
Regions
About West Midlands Trains
For further information on this release, email press.office@wmtrains.co.uk
West Midlands Trains operates both West Midlands Railway and London Northwestern Railway services.
- London Northwestern Railway services operate between Liverpool and Birmingham, and on the West Coast Main Line to and from London Euston.
- West Midlands Railway services operate to destinations across the West Midlands via Birmingham New Street and Birmingham Snow Hill.
For more information on these services visit westmidlandsrailway.co.uk or londonnorthwesternrailway.co.uk
If you have been sent this press release, this is because we believe this to be of interest to you.
To sign up for all future releases, visit our newsroom and subscribe to our updates. You can unsubscribe to our releases at any time.